Davide Zerbetto commented on APP-1425:
--------------------------------------
What went well:
* we succeeded in developing foreseen stories;
What to improve:
* the process of introducing Knowage is slow: we still don't have an entry for Knowage in the backlog;
* due easter holidays, and some unexpected tasks, the progress has been slower than expected;
* due to unexpected tasks, the developments have been delayed.
> FIWARE.WorkItem.Apps.Coordination.Agile.Sprint-631.Retrospective
> ----------------------------------------------------------------
>
> Key: APP-1425
> URL: https://jira.fiware.org/browse/APP-1425
> Project: Chp - Apps
> Issue Type: WorkItem
> Components: _Coordination
> Reporter: Backlog Manager
> Assignee: Davide Zerbetto
> Fix For: Sprint 6.3.1
>
>
> # Drawn {color:red} Chapter Summary Retrospective{color} from {color:blue} Enablers' Retrospectives{color}
> # Retrospective Pattern:
> #* {color:blue}What went well{color}
> #** identify aspects working smoothly
> #* {color:blue}What to improve{color}
> #** identify aspects making progress difficult
--