[Backlogmanager] [FIWARE-JIRA] (OPS-1614) FIWARE.WorkItem.Ops.Coordination.Agile.Sprint-623.Retrospective

Federico Michele Facca (JIRA) fiware-ops-jira at jira.fiware.org
Fri Mar 31 17:39:02 CEST 2017


    [ https://jira.fiware.org/browse/OPS-1614?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=59513#comment-59513 ] 

Federico Michele Facca commented on OPS-1614:
---------------------------------------------

What went well
- In general good progresses in the activities.

What to improve
- Ownership of Dash should be changed.
- Improve the planning of Deploy activities and the management of unpredictable external issues.
- Health should better dimension the activities since several issues were not resolved.
- Progress on issues depending on pending actions by nodes: We have 8 Impeded issues due to we cannot resolve them due to pending actions from FIWARE Lab nodes mainly.

> FIWARE.WorkItem.Ops.Coordination.Agile.Sprint-623.Retrospective
> ---------------------------------------------------------------
>
>                 Key: OPS-1614
>                 URL: https://jira.fiware.org/browse/OPS-1614
>             Project: Chp -- Ops
>          Issue Type: WorkItem
>          Components: _Coordination
>            Reporter: Backlog Manager
>            Assignee: Federico Michele Facca
>             Fix For: Sprint 6.3.1
>
>
> # Drawn {color:red} Chapter Summary Retrospective{color} from {color:blue} Enablers' Retrospectives{color} 
> # Retrospective Pattern:
> #* {color:blue}What went well{color}
> #** identify aspects working smoothly
> #* {color:blue}What to improve{color}
> #** identify aspects making progress difficult



--
This message was sent by Atlassian JIRA
(v6.4.1#64016)