[Backlogmanager] [FIWARE-JIRA] (LAB-2987) FIWARE.WorkItem.Lab.Spain.Agile.Sprint-732.Close

Fernando Lopez (JIRA) fiware-lab-jira at jira.fiware.org
Wed May 30 09:35:01 CEST 2018


    [ https://jira.fiware.org/browse/LAB-2987?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=109924#comment-109924 ] 

Fernando Lopez commented on LAB-2987:
-------------------------------------

* {color:blue}What went well{color}
** Activity to migrate the node to mitaka.
** Security issues detected in Spain resources.
** Support to Noida.
* {color:blue}What to improve{color}
** Nothing special.


> FIWARE.WorkItem.Lab.Spain.Agile.Sprint-732.Close
> ------------------------------------------------
>
>                 Key: LAB-2987
>                 URL: https://jira.fiware.org/browse/LAB-2987
>             Project: Chp -- Lab
>          Issue Type: WorkItem
>          Components: NODE_SPAIN
>            Reporter: Backlog Manager
>            Assignee: Fernando Lopez
>             Fix For: Sprint 7.3.2
>
>
> +Activities requested to {color:red}Close{color} {color:blue}*Sprint 7.3.2*{color}+
> # Close your backlog issues finished during the sprint
> # Add any work item not foreseen but arisen during the sprint 
> # Provide your retrospective in this specific issue created for this purpose by adding a comment
> {color: red}Deadline = 31-05-2018 at 18:00 {color}
> +Reminders:+
> # Issues left open are moved forward to next sprint automatically at sprint closing time
> # WorkItems almost finished can be closed, and then cloned for the next sprint
> # Retrospective Pattern:
> #* {color:blue}What went well{color}
> #** identify aspects working smoothly
> #* {color:blue}What to improve{color}
> #** identify aspects making progress difficult



--