I have reviewed the periodic progress report for Y1 of the FI-NEXT
project with regards to WP3 activities (FIWARE Evolution) and have
introduced a number of changes I would like to summarize here:
* I incorporated a general description of overall WP activities at the
beginning of the section and have relied on the provided text to
simplify wording in the individual reports by partners. Same applies
regarding the overall introduction provided for each task.
* Task 3.6 will be merged into task 3.1 for reasons described in the
introduction of task 3.1. Consequently, activities reported by UPM
and to be reported by APInf within task 3.6 have been moved to the
reporting in task 3.1
* Reporting of activities from UPM regarding Cygnus and Comet-STH have
been provided linked to task 3.1
* Reporting of activities linked to Perseo CEP have been moved from
task 3.1 to task 3.5
* Activities of Naveatec have been concentrated in task 3.5 (therefore
the reporting made on task 3.1 has been moved to this task)
* The FIWARE Foundation has been included as partner carrying out
activities linked to task 3.2 since it looked rather weird that
Orange were reporting activities linked to the ETSI CIM ISG without
the FIWARE Foundation doing the same.
* Activities from DFKI have concentrated on task 3.1 and 3.2.
* Activities from UPM linked to Wirecloud and Cosmos have been placed
on task 3.5
* Regarding coaching activities, I have adopted the same wording for
the reporting by each partner in order to make it look more
homogeneous. For each partner, I have specified the concrete
companies within IMPACT Growth they were assigned as coaches. Note
that report on coaching activities regarding NaevaTec or Engineerig
are not listed in task 3.1.
I believe this is all. As you can see, I have mostly moved the
reporting of certain activities from one task to another within the same
WP because this helped to construct a more coherent speech. Please
read the overall reporting of the whole WP as well as the introduction
per tasks to get a view on that speech.
Unless there is any objection, this will be the report for WP3
activities that will go as part of the overall periodic progress report.
Cheers,
--
Document
Juanjo Hierro
Chief Technology Officer
juanjose.hierro at fiware.org <mailto:juanjose.hierro at fiware.org>
www.linkedin.com/in/jhierro <https://www.linkedin.com/in/jhierro>
Twitter: @fiware <https://twitter.com/fiware> @JuanjoHierro
<https://twitter.com/JuanjoHierro>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.fiware.org/private/fi-next/attachments/20180807/3e225f78/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: foundation-logo.png
Type: image/png
Size: 8201 bytes
Desc: not available
URL: <https://lists.fiware.org/private/fi-next/attachments/20180807/3e225f78/attachment.png>
You can get more information about our cookies and privacy policies clicking on the following links: Privacy policy Cookies policy