Hi Jonne

First: Today 15:00 is the deadline for the Technical Roadmap Delivery
https://forge.fi-ware.eu/plugins/mediawiki/wiki/fiware/index.php/Roadmap_of_Advanced_Middleware_and_Web_UI
So all the Features should be there in the wiki-page in the correct release they are delivered.
To update the tracker we have time until Friday 18:00 [very latest]

Regarding the scheduling of the  Features/Sprints:
In principle it is very simple (there are 2 main rules):
- All the work done in December is in Sprint 3.2.3, All the work done in January is in Sprint 3.3.1, February Sprint 3.3.2, ...
- Release numbers always have to match the sprint numbers. If you have Sprint 3.3.x Release has to be 3.3. If you have Sprint 3.2.x Release has to be 3.2.

Now to the confusing part.
- R3.2 (SW & Guides) should have been finished in December (Sprint 3.2.3 Release 3.2). That we are working on this now in January is already an „extension“.
- So we have to schedule the WorkItems for the guides & SW release, … for Sprint 3.3.1 / Release 3.3. This is, because the reporting tools work this way.
- That we are working on the documentation for Release 3.2 can be declared in the description field of the WorkItem (not in the Release field).
  (See also my email from January 24th and January 27th)

If you finished implementing a feature work item in December it should be set to closed with Release 3.2. 

This is valid for all GEis.

Christof

Am 29.01.2014 um 12:18 schrieb Jonne Nauha <jonne at adminotech.com>:

> What? We have been talking the whole time that we make release 3.2 in January. So now it has changed to 3.3? I do understand that the current sprint is 3.3.1 but I thought we are making a delayed 3.2 release and the future releases are 3.3.x. We also have all marked the features to 3.2 release on the roadmap wiki. Why would it suddenly be that all those features are in the 3.3 release?
> 
> I'm referring to your note to Antti and Cvetan. I also have all features completed now marked to the 3.2 release and the 3.2.x sprints. There are also loads of 3.2.x release/sprint entries in the other backlog features/work items from other companies.
> 
> If all this needs to be changed before 15:00 now would be the time to tell about it. I haven't gotten the impression at any point that we are making a 3.3.x release now.
> 
> Best regards,
> Jonne Nauha
> Meshmoon developer at Adminotech Ltd.
> www.meshmoon.com
> 
> 
> On Wed, Jan 29, 2014 at 12:43 PM, Christof Marti <mach at zhaw.ch> wrote:
> Hi 
> 
> Following a short summary of the Action Points from todays meeting:
> (for details see the topics in todays minutes: https://docs.google.com/document/d/1q6Of53kd4kGISS1mGKmw68y7eVKVcV3B4cyF2ks1JMY/edit)
> 
> [Today Wed 29th January before 15:00] All GEi owner: Check and update Technical roadmap
> https://forge.fi-ware.eu/plugins/mediawiki/wiki/fiware/index.php/Roadmap_of_Advanced_Middleware_and_Web_UI
> Is it ies (Features for R3.1,R3.2, R3.3)
> Are the Features for Release 3.3 available?
> Is the textual description of the features in the first half of the document correct/missing?
> Specially check/update the 3D-UI implementations (XML3D & WebTundra) which now are split up in separate entries (Torsten, Toni)
> [Today Wed 29th January EOB] All GEi owner: Software packages available in Files section of FI-WARE or FI-WARE PPP restricted
> And link to release container copied to WP13 Dashboard/Software/delivery 
> https://docs.google.com/spreadsheet/ccc?key=0Auieh_fs3EUxdFVvY19ab1lFRDRUaTBrUXlpYzBVRlE#gid=17
> [Today Wed 29th January] Affected GEi owners: Fix remaining guides (orange) and request new review from Christof
> https://docs.google.com/spreadsheet/ccc?key=0Auieh_fs3EUxdFVvY19ab1lFRDRUaTBrUXlpYzBVRlE#gid=17
> [Today Wed 29th January] Cvetan, Antti: Fix errors in historic section of tracker
> As much I can see, only the Release number is wrong. Should be Release 3.3 instead of Release 3.2.
> [Thursday 30th January] All GEi owners: Check tracker entries of your GE and enhance backlog & roadmap (see examples in minutes)
> [Friday 31th January before 18:00] All GEi owner: Sprint 3.3.1 is ending. 
> Close finished entries and check schedule for all open entries
> 
> Thanks for keeping the Deadlines.
> Christof
> ----
> InIT Cloud Computing Lab - ICCLab http://cloudcomp t of Applied Information Technology - InIT
> Zurich University of Applied Sciences - ZHAW
> School of Engineering 
> Phone: +41 58 934 70 63
> Skype: christof-marti
> 
> Am 29.01.2014 um 09:13 schrieb Christof Marti <mach at zhaw.ch>:
> 
>> Hi
>> 
>> Here is the agenda/minutes of todays WP13 call:
>> https://docs.google.com/document/d/1q6Of53kd4kGISS1mGKmw68y7eVKVcV3B4cyF2ks1JMY/edit
>> 
>> We have to deliver many items this week (some even today). 
>> GEi owners or please attend the meeting or send a deputy and check the minutes.
>> 
>> I will open the telco session at 10:00 CET.
>> 
>> Best regards
>> Christof
>> ----
>> InIT Cloud Computing Lab - ICCLab http://cloudcomp.ch
>> Institut of Applied Information Technology - InIT
>> Zurich University of Applied Sciences - ering 
>> 
>> Phone: +41 58 934 70 63
>> Skype: christof-marti
> 
> 
> _______________________________________________
> Fiware-miwi mailing list
> Fiware-miwi at lists.fi-ware.eu
> https://lists.fi-ware.eu/listinfo/fiware-miwi
> 
> 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.fiware.org/private/fiware-miwi/attachments/20140129/c65e737c/attachment.html>


More information about the Fiware-miwi mailing list

You can get more information about our cookies and privacy policies clicking on the following links: Privacy policy   Cookies policy