[Fiware-pcc] Proposal on PMs reallocation across several WPs

BISSON Pascal pascal.bisson at thalesgroup.com
Mon Mar 26 11:06:18 CEST 2012


Dear Juanjo,

Since so far there the date of our next audio PCC conference has not been yet announced let me come back to you with comments from our Thales side.

As it was announced and also discussed at last GA Thales has decided to withdraw from WP5 and move its effort (25PM) to WP4 (Cloud Hosting).

As for the rest we also announced in our reporting to Javier that we will withdraw from WP6 to move our effort to WP8 and that TRT-FR has decided to leave the consortium their asset being not selected.


So just to summarize the Movements from our Thales side:

·         25 PMs of Thales (TCF) to be moved from IoT (WP5) to Cloud Hosting (WP4)

·         7 PMs of Thales (TCF) to be moved from WP6 to WP8

Last but not least:

·         TRT-FR (one of the third parties of TCF) has decided to withdraw from FI-WARE. TRT-FR effort (7PMs) would also be moved to WP8.


Please integrate those movements and changes in the context of amendment under preparation.

Best Regards,
Pascal


De : fiware-pcc-bounces at lists.fi-ware.eu [mailto:fiware-pcc-bounces at lists.fi-ware.eu] De la part de Juanjo Hierro
Envoyé : mardi 13 mars 2012 17:04
À : fiware-pcc at lists.fi-ware.eu
Objet : [Fiware-pcc] Proposal on PMs reallocation across several WPs

Hi all,

  I believe that is becoming urgent to fix some movements regarding PMs across several WPs that I believe would go for the benefit of the whole project.  They would indeed mean that partners are focused on a more concrete number of WPs and tasks and I believe this always leads to a more effective usage of resources.

  A key enabler of these movements is that NSN-Germany has announced that they will leave the IoT WP so, therefore, part of their PMs could be used to fix some of the conflicts that were blocking a decision.   I want to thank Thierry, as leader of the IoT WP, for allowing me to make this proposal taking part of these PMs.

  The movements I propose to apply and the resulting balance are the following:

 *   Movements:
    *   20 PMs of Orange-FT would be moved from Cloud to IoT
    *   25 PMs of TID would be moved from Security to Cloud to cover the gap from the previous movement by Orange, the remaining 15PMs in Security are left there
    *   25 PMs of Thales would be moved from IoT to Security to cover the gap by TID in Security
    *   15 PMs originally assigned to NSN-Germany would be transferred to TID to reinforce our involvement in IoT chapter
 *   Resulting balance:
    *   Security: same PMs as before, with stronger presence of Thales.  15PMs pending of allocation and contributions from TID pending to be reformulated (we believe they can be just dropped)
    *   Cloud: +5PMs
    *   IoT: -25 PMs from Thales + 20 PMs from Orange-FT= -5 PMs compared with what had before, plus 15 PMs pending of reallocation from NSN-Germany
  Please let us know whether you would object to these changes before mid next week.   If not, we would prepare an amendment of the DoW reflecting them.  With a bit of luck, those changes may enter the current amendment under negotiation (although we won't delay closing the current one under negotiation, it might be the case that this change fits in)

  Best regards,

-- Juanjo


________________________________
Este mensaje se dirige exclusivamente a su destinatario. Puede consultar nuestra política de envío y recepción de correo electrónico en el enlace situado más abajo.
This message is intended exclusively for its addressee. We only send and receive email on the basis of the terms set out at
http://www.tid.es/ES/PAGINAS/disclaimer.aspx
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.fiware.org/private/fiware-pcc/attachments/20120326/b9cb3fbd/attachment.html>


More information about the Fiware-pcc mailing list

You can get more information about our cookies and privacy policies clicking on the following links: Privacy policy   Cookies policy