Dear partners,

 

I would like to report the contents of the meetings of the FI PPP that have been held this week in Brussels.

 

Meetings: Use Case meeting & Steering Board of the FI PPP

When & Where: 26th-27th March, Brussels

Who: representatives of all the projects of the FI PPP, including FI-WARE, INFINITY, the Use Cases and CONCORD

 

A depict briefly the discussions held in Brussels pointing out some VERY RELEVANT issues for FI-WARE, but you can find attached the official minutes circulated today by CONCORD (as well as the agenda and some complementary material).

 

·         FI PPP Working Groups

o    The dissemination WG is working as expected and the main topic now is the organization of the FI PPP presence in Aalborg. In the last years there was an event focused on Future Internet besides FI (the so called Future Internet Conference). This year this will not happen, but the EC is organizing kind-of Infoday of the Second Call for proposals of the FI PPP. How to organize it (which contents and our role there is still unclear, but I will keep you informed). FI-WARE in any case will be present in a very interesting session in FIA.

o    In the last SB a new WG was approved, focused on Business models and exploitation. My colleagues Juan (WP11 leader) and Carmen are following it on behalf of FI-WARE. They will have a face-to-face meeting in Aalborg

o    A new WG was proposed in this SB, this time focused on policy and regulation (see further information in the minutes)

·         Second Phase of the FI PPP & support from FI-WARE

o    One of the hot topics of these meetings has been the support that FI-WARE will provide to the Use Case projects in their trials

o    Questions that Use Cases have made in a quite aggressive way (especially because they are not satisfied about the answers by FI-WARE are)

§  Which test bed will they use for their trials? What will be the availability of the test bed in Seville for their initial pilots and furthermore, the trials that will happen in Phase II (even though no current project is confirmed for the next phase)

§  Kind of support FI-WARE will provide (in terms of QoS, which functionalities and to which extend they can trust the performance of the platform from the point of view of scalability or other issues needed for the tests?

§  Support also in terms of training to technicians in the use case projects

§  With respect to the Phase II of the PPP there was also a difficult discussion related to the responsibilities of each project: who will instantiate the Core Platform, and so on and so forth

 

Please, have a look at the attached PPT used by Werner Mohr (from NSN) and representing the FINSENY project in the SB that shows quite clearly major concerns of the Use Case projects with respect to FI-WARE.

 

I can tell you that they are worried about possible delays and reliability of FI-WARE and all of them have their plan B. I tried to show as much collaboration as possible and openness from FI-WARE, still maintaining the statements of our project with respect to our responsibilities vis-à-vis those issues.

However, I realized that Peter Fatelnig (who attended the SB) was not happy about this approach and he wants that Use Case projects use the SB a decision-support body to put pressure on FI-WARE regarding delays, availability and reliability of the project results. I think it is fair but requires that we face these issues in a serious way-.

 

I explained that the AB is working on a paper that will give positions on the main issues already identified by the INIFNITY project in a former paper that has been used as basis for discussion. Juanjo, the commitment is that this paper (with clear commitments of FI-WARE) is ready by Mid-April and is distributed to the SB for discussion and decisions.

 

I will explain in more detail all the contents in the next PCC teleconference. Meanwhile do not hesitate to come back to me for any doubt you may have.

 

Best regards, 

 

Nuria de Lama

 

Research & Innovation 

Representative to the European Commission

  

T +34 91214 9321

F +34 91754 3252 

nuria.delama at atosresearch.eu <mailto:nuria.delama at atosresearch.eu> 

Albarracín 25

28037 Madrid

Spain

www.atosresearch.eu <http://www.atosresearch.eu> 

es.atos.net 

  

 

 

________________________________

 

------------------------------------------------------------------
This e-mail and the documents attached are confidential and intended 
solely for the addressee; it may also be privileged. If you receive 
this e-mail in error, please notify the sender immediately and destroy it. 
As its integrity cannot be secured on the Internet, the Atos 
group liability cannot be triggered for the message content. Although 
the sender endeavours to maintain a computer virus-free network, 
the sender does not warrant that this transmission is virus-free and 
will not be liable for any damages resulting from any virus transmitted. 

Este mensaje y los ficheros adjuntos pueden contener informacion confidencial 
destinada solamente a la(s) persona(s) mencionadas anteriormente 
pueden estar protegidos por secreto profesional. 
Si usted recibe este correo electronico por error, gracias por informar 
inmediatamente al remitente y destruir el mensaje. 
Al no estar asegurada la integridad de este mensaje sobre la red, Atos 
no se hace responsable por su contenido. Su contenido no constituye ningun 
compromiso para el grupo Atos, salvo ratificacion escrita por ambas partes. 
Aunque se esfuerza al maximo por mantener su red libre de virus, el emisor 
no puede garantizar nada al respecto y no sera responsable de cualesquiera 
danos que puedan resultar de una transmision de virus. 
------------------------------------------------------------------
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.fiware.org/private/fiware-pcc/attachments/20120328/b3596c90/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.gif
Type: image/gif
Size: 78 bytes
Desc: image001.gif
URL: <https://lists.fiware.org/private/fiware-pcc/attachments/20120328/b3596c90/attachment.gif>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.gif
Type: image/gif
Size: 816 bytes
Desc: image002.gif
URL: <https://lists.fiware.org/private/fiware-pcc/attachments/20120328/b3596c90/attachment-0001.gif>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Access to Core Platform_Final.ppt
Type: application/vnd.ms-powerpoint
Size: 569856 bytes
Desc: Access to Core Platform_Final.ppt
URL: <https://lists.fiware.org/private/fiware-pcc/attachments/20120328/b3596c90/attachment.ppt>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: FI PPP Steering Board Minutes 2012-03-27 v1.0.doc
Type: application/msword
Size: 610304 bytes
Desc: FI PPP Steering Board Minutes 2012-03-27 v1.0.doc
URL: <https://lists.fiware.org/private/fiware-pcc/attachments/20120328/b3596c90/attachment.doc>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: FI PPP Steering Board Agenda 2012-03-27 v1.0.doc
Type: application/msword
Size: 571904 bytes
Desc: FI PPP Steering Board Agenda 2012-03-27 v1.0.doc
URL: <https://lists.fiware.org/private/fiware-pcc/attachments/20120328/b3596c90/attachment-0001.doc>


More information about the Fiware-pcc mailing list

You can get more information about our cookies and privacy policies clicking on the following links: Privacy policy   Cookies policy