Dear Juanjo,
below the requested info.

I was wondering if you sent to the PO the mail on the roadmap.

Thx and regards,

M.

Il 17/09/2012 08:37, Juanjo Hierro ha scritto:
> Hi all,
>
>   I'm currently in Israel and despite I thought I was going to be able 
> to connect our regular follow-up confcall I won't finally be able to 
> do so for logistic reasons.
>
>   Therefore, the joint follow-up confcall today will be cancelled.   I 
> believe we can follow-up progress of the activities off-line this 
> week.  In this respect, I would like to remind you the following 
> critical APs (see also requests about reporting):
>
>   * Fix information published on the Catalogue about FI-WARE GEs
>     available on the FI-WARE Testbed so that it complies with defined
>     templates (Matteo, please report on the status of this)
>
[MM] Status of the GEs on the FI-WARE Catalogue:
- MEDIATOR GE not yet compliant with the template.
- Wirecloud Mashup Platform not yet compliant with the template.
- Gateway Device Management GE not yet compliant with the template.
- Things Management GE not yet compliant with the template.
- Data Handling not yet compliant with the template.
>
>   * Stefano to give Matteo a list of people in the Testbed team that
>     would keep read privileges on entries associated to GEs that are
>     under progress (Stefano or Matteo, please report on the status of
>     this)
>
No news on this.
>
>   * Some GEs were planned to be available mid September: QueryBroker,
>     Semantic Annotation Support, Ericsson Composition Editor and
>     Gateway Device Management GE (Carlos, Uwe and Thierry, please
>     report on the status of the GEs in this list within your chapter)
>
[MM] Gateway Device Management GE is already published according to the 
info I have from the Testbed. Should I hide this GE from the catalogue?
>
>   * All chapters were supposed to close a stable version of the
>     "Architecture and Open Specifications" so we could carry out a
>     second peer-review of them starting on September 11, 12:00 CET.  
>     It is planned that reviewing chapters deliver the results of their
>     revision, using the provided forms, by September 20th.   (please,
>     all WPLs to report on the status of this)
>   * Planning of September Sprint by each Chapter reflected on the
>     corresponding Chapter tracker.   This was a must and it was
>     expected to be finished by Thursday last week at the latest.   We
>     will check the tracker and get back to you about any issue we may
>     find.   Note that those partners that do not have any assignment
>     are supposed that are not working during the Sprint, or keeping a
>     minimum level of activity, therefore their costs reports may be
>     rejected.
>
>
> It would be great if Uwe Riss from SAP can send us some brief report 
> on how was the InfoDay in Brussels. Here, I would like to share with 
> the rest of WPLs/WPAs that we, SAP and Telefonica, took advantage of 
> the need to make a presentation in the InfoDay to produce two valuable 
> elements now in the public wiki:
>
>   * A "Quick FI-WARE tour" wiki page that may help people to navigate
>     through the big ocean of FI-WARE available information
>   * A "FI-WARE FAQ" wiki page that may be also helpful in
>     understanding of FI-WARE
>
>
> Regarding the FI-PPP AB last week, I would like to highlight the 
> following topics (I will distribute the minutes as soon as a stable 
> draft is available):
>
>   * The shared spreadsheet about inteded usage of the FI-WARE GEs by
>     Use Case projects in phase 1 will be updated because a new "state"
>     will be introduced (not relevant at this point but in the near
>     future, taking into account that the document will be a living
>     document).    I believe that the notes in the spreadshet are
>     self-explanatory, so you just need to revisit
>       o https://docs.google.com/spreadsheet/ccc?key=0AqGGeaQGro3fdEd6bGhLQWtNai1jeGN5UnJMeEdxZ0E#gid=0
>
>
>   * It was agreed that we can add a given Use Case project as
>     "stakeholder" of all features of a GE for which the project has
>     assigned label "U" in the spreadsheet of the previous point (which
>     means that they have already taken the GE into consideration in
>     their design).   Chapter leaders should monitor the status of this
>     table because, hopefully, some "E"s will transit into "U"s
>
>   * Architecture documents delivered by the Use Case projects have
>     been uploaded on the FI-WARE docman system.  You can find them
>     within the folder titled "FI-PPP UC Projects Architecture
>     Documentation" (note that you should have logged in FusionForge
>     first)
>
>   * The issue about Secured Access to the FI-WARE Testbed was labeled
>     as critical so FI-WARE were requested to provide a solution as
>     soon as possible.   I will send a more elaborated email on this
>     later today.
>
>   * I reported that we have started to take care of tickets issued by
>     UC projects on the "FI-WARE General Support" tracker but let me
>     share with you that some of them share their concern that most of
>     the tickets changed to the "assigned" state right before the
>     FI-PPP AB meeting after more than one month being open without
>     feedback.   Therefore, some UC projects suspect it was a
>     "cosmetic" change so they will keep an eye on how this evolves ...
>     Therefore, we have to start working on it in a regular, constant,
>     basis
>
>   * I commit to prepare a paper and presentation on how applications
>     can be designed to take advantage of the integration of the
>     different Data/Context Management GEs planned in Release 2 and the
>     ability to support an Open Data approach.   I will target a
>     virtual workshop with UC projects on September 25th.
>
>
>   Best regards,
>
> -- Juanjo
>
> -------------
> Product Development and Innovation (PDI) - Telefonica Digital
> website:www.tid.es
> email:jhierro at tid.es
> twitter: twitter.com/JuanjoHierro
>
> FI-WARE (European Future Internet Core Platform) Chief Architect
>
> You can follow FI-WARE at:
>    website:http://www.fi-ware.eu
>    facebook:http://www.facebook.com/pages/FI-WARE/251366491587242
>    twitter:http://twitter.com/FIware
>    linkedIn:http://www.linkedin.com/groups/FIWARE-4239932
>
> ------------------------------------------------------------------------
>
> Este mensaje se dirige exclusivamente a su destinatario. Puede 
> consultar nuestra política de envío y recepción de correo electrónico 
> en el enlace situado más abajo.
> This message is intended exclusively for its addressee. We only send 
> and receive email on the basis of the terms set out at:
> http://www.tid.es/ES/PAGINAS/disclaimer.aspx
>
>
> _______________________________________________
> Fiware-wpl mailing list
> Fiware-wpl at lists.fi-ware.eu
> http://lists.fi-ware.eu/listinfo/fiware-wpl

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.fiware.org/private/fiware-wpa/attachments/20120917/dee9c56c/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: matteo_melideo.vcf
Type: text/x-vcard
Size: 368 bytes
Desc: not available
URL: <https://lists.fiware.org/private/fiware-wpa/attachments/20120917/dee9c56c/attachment.vcf>


More information about the Fiware-wpa mailing list

You can get more information about our cookies and privacy policies clicking on the following links: Privacy policy   Cookies policy