[Fiware-wpl] Roadmap and backlog reviews

MANUEL ESCRICHE VICENTE mev at tid.es
Wed Sep 18 19:59:32 CEST 2013


Dear Partners,

Please, find below links to reviews done over the trackers.

WP3-Apps(@Markus)
https://forge.fi-ware.eu/docman/view.php/27/2817/FIWARE.backlog.apps.review.20130918-1831.xlsx
Progress from last report (Tracker:69.8%->69.2%; Flat structure:89.9%->87.2%; Wiki:18,9%->19.6%)
Markus, Indicators show little progress, but some on Tracker and Structure.
Please, have a look at WP6, which has shown progress is possible on Structure, they started with 94% and have progressed to 36%

WP4-Cloud(@Alex)
https://forge.fi-ware.eu/docman/view.php/27/2818/FIWARE.backlog.cloud.review.20130918-1831.xlsx
Progress (Tracker:75,6%->74,9%; Flat Structure:23.2%->23.2%; Wiki: 56.7%->57.4%)
Alex, Indicators show almost no progress. I want you to consider WP6 progress.

WP5-IoT(@Thierry)
https://forge.fi-ware.eu/docman/view.php/27/2821/FIWARE.backlog.iot.review.20130918-1832.xlsx
Progress (Tracker: 99.6%->99.2%; Flat Structure: 34.1%->30.8%; Wiki:39,76%->37.75%)
Thierry, I appreciate the progress on structure and the wiki as well

WP6-Data(@Sergio)
https://forge.fi-ware.eu/docman/view.php/27/2819/FIWARE.backlog.data.review.20130918-1831.xlsx
Progress (Tracker: 73.4%->68.2%; Flat Structure:47.2%->36.3%; 65.46% -> 63.28%)
Sergio, Congratulations again!!! For the amazing progress on structure, and also on the tracker.

WP7-I2nd(@Pier)
https://forge.fi-ware.eu/docman/view.php/27/2820/FIWARE.backlog.i2nd.review.20130918-1832.xlsx
Progress (Tracker: 61,7%->59.1%; Flat Structure 27.6%->23.9%; 34.3%->32.3%)
Pier, I appreciate the progress on tracker, structure (well done!!!) and wiki

WP8-Security(@Pascal)
https://forge.fi-ware.eu/docman/view.php/27/2822/FIWARE.backlog.security.review.20130918-1832.xlsx
Progress (Tracker:75.9%->76,0%; Flat Structure 59.1%->59.1%; 72.15%->72.33%)
Pascal, Last month progress was amazing in this chapter, but there seem to be no progress this month.

I know it has been especially difficult to progress during last three months due to several factors: finishing R2, holidays and the campus party mainly but I think it's time to focus on progressing by identifying the roadmap and by fixing the backlog; this way will pave the path to quickly advance towards the objectives during RP3.

Let me remind you there're meetings scheduled next week (24-30 Sept) for reviewing the backlog status. Additionally I want to emphasize the backlog has a delivery scheduled by 30th October. I would appreciate having a similar effort to the one done by the Data Chapter so that the backlog delivery is in much better status.

Let me remind you of the roadmap as well. Updating it was a task started at the beginning of July (08), there's need to close this task and update the roadmap wiki. Let me inform you that next sprint planning meeting will consider R3 roadmap. These meeting will be held by 7-11 October.

Thanks for cooperation!!

If anything, please, let me know.
Kind regards,
Manuel

----------------------------
Manuel Escriche Vicente
Agile Project Manager/Leader
FI-WARE Initiative
Telefónica Digital
Parque Tecnológico
C/ Abraham Zacuto, 10
47151 - Boecillo
Valladolid - Spain
Tfno: +34.91.312.99.72
Fax: +34.983.36.75.64
http://www.tid.es<http://www.tid.es/>


________________________________

Este mensaje se dirige exclusivamente a su destinatario. Puede consultar nuestra política de envío y recepción de correo electrónico en el enlace situado más abajo.
This message is intended exclusively for its addressee. We only send and receive email on the basis of the terms set out at:
http://www.tid.es/ES/PAGINAS/disclaimer.aspx
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.fiware.org/private/fiware-wpl/attachments/20130918/03a936c5/attachment.html>


More information about the Fiware-wpl mailing list

You can get more information about our cookies and privacy policies clicking on the following links: Privacy policy   Cookies policy