Dear Partners, The planning activity for Sprint 6.4.2 was delayed a little due to summer holidays. Here you can see the summarize of it: Summary: -Tech: 313 tickets -Lab: 87 tickets *Total: 400 tickets* Tech: http://backlog.fiware.org/chapters/overview Contributions from Chapters: About I2ND, you shouldn’t understand they are doing more activity than others. Many of their items are rolling sprint after sprint. Lab: http://backlog.fiware.org/lab/backlog Kind regards, Fernando -- Fernando López Interim FIWARE Scrum Master Franklinstrasse 13A 10587 Berlin - Germany fernando.lopez at fiware.org <mailto:fernando.lopez at fiware.org> www.fiware.org <http://www.fiware.org> -------------- next part -------------- An HTML attachment was scrubbed... URL: <https://lists.fiware.org/private/fiware/attachments/20170822/a3d2c8e1/attachment-0001.html> -------------- next part -------------- A non-text attachment was scrubbed... Name: bbdpiaibkppghihg.png Type: image/png Size: 111828 bytes Desc: not available URL: <https://lists.fiware.org/private/fiware/attachments/20170822/a3d2c8e1/attachment-0003.png> -------------- next part -------------- A non-text attachment was scrubbed... Name: dnjemjhmoaboijik.png Type: image/png Size: 101481 bytes Desc: not available URL: <https://lists.fiware.org/private/fiware/attachments/20170822/a3d2c8e1/attachment-0004.png> -------------- next part -------------- A non-text attachment was scrubbed... Name: lpemnenaejjkplae.png Type: image/png Size: 93490 bytes Desc: not available URL: <https://lists.fiware.org/private/fiware/attachments/20170822/a3d2c8e1/attachment-0005.png>
You can get more information about our cookies and privacy policies clicking on the following links: Privacy policy Cookies policy