Dear Partners,
The planning activity for Sprint 6.4.2 was delayed a little due to
summer holidays. Here you can see the summarize of it:
Summary:
-Tech: 313 tickets
-Lab: 87 tickets
*Total: 400 tickets*
Tech:
http://backlog.fiware.org/chapters/overview
Contributions from Chapters:
About I2ND, you shouldn’t understand they are doing more activity than
others. Many of their items are rolling sprint after sprint.
Lab:
http://backlog.fiware.org/lab/backlog
Kind regards,
Fernando
--
Fernando López
Interim FIWARE Scrum Master
Franklinstrasse 13A
10587 Berlin - Germany
fernando.lopez at fiware.org <mailto:fernando.lopez at fiware.org>
www.fiware.org <http://www.fiware.org>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.fiware.org/private/fiware/attachments/20170822/a3d2c8e1/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: bbdpiaibkppghihg.png
Type: image/png
Size: 111828 bytes
Desc: not available
URL: <https://lists.fiware.org/private/fiware/attachments/20170822/a3d2c8e1/attachment-0003.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: dnjemjhmoaboijik.png
Type: image/png
Size: 101481 bytes
Desc: not available
URL: <https://lists.fiware.org/private/fiware/attachments/20170822/a3d2c8e1/attachment-0004.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: lpemnenaejjkplae.png
Type: image/png
Size: 93490 bytes
Desc: not available
URL: <https://lists.fiware.org/private/fiware/attachments/20170822/a3d2c8e1/attachment-0005.png>
You can get more information about our cookies and privacy policies clicking on the following links: Privacy policy Cookies policy