Alex Glikson GLIKSON at il.ibm.com
Wed Jun 27 08:58:14 CEST 2012


Reminder -- please, complete the action items below.

On today's agenda:
- project review impressions
- deliverables due end of June -- test plan, user & programmer guide, 
install & admin guide (
https://forge.fi-ware.eu/plugins/mediawiki/wiki/fi-ware-private/index.php/FiwareDeliverables 
)

Regards,
Alex

====================================================================================================
Alex Glikson
Manager, Cloud Operating System Technologies, IBM Haifa Research Lab
http://w3.haifa.ibm.com/dept/stt/cloud_sys.html | 
https://www.research.ibm.com/haifa/dept/stt/cloud_sys.shtml 
Email: glikson at il.ibm.com | Phone: +972-4-8281085 | Mobile: 
+972-54-6466667 | Fax: +972-4-8296112

----- Forwarded by Alex Glikson/Haifa/IBM on 27/06/2012 08:21 AM -----

From:   Alex Glikson/Haifa/IBM at IBMIL
To:     "fiware-cloud at lists.fi-ware.eu" <fiware-cloud at lists.fi-ware.eu>, 
Date:   13/06/2012 05:15 PM
Subject:        [Fiware-cloud] minutes
Sent by:        fiware-cloud-bounces at lists.fi-ware.eu



Summary of today's meeting: 
Date: 13/6/2012 
Attendees: IBM, TID, UPM, Technicolor, INRIA 
Minutes: 
The education sessions with the use-cases were very interesting and 
insightful. 
Based on the feedback received from the use-cases, it is being considered 
to precede the delivery of Object Storage GE from August to July. 
Moreover, following the 'popularity' of the cloud proxy concept, we are 
considering an Open Call topic that would ease the usage of CP resources 
by UC applications 
FI-WARE project review is going to take place in Brussels next week. Only 
20 minutes are allocated to present the entire year of work in each 
chapter, so don't expect to go into much detail. 
We need to make sure that our tracker properly represents the progress of 
our work, so that it can be verified if requested. 
Action Item [All, by Tue next week, 19/6]: review & update tracker, make 
sure all the features and stories are in place, and are properly assigned 
to releases and sprints (past and current).
We need to finish our work on all the 'month 12' deliverables by the end 
of June -- including GEs first implementation (naturally), as well as 
deliverables associated with each GE -- installation & admin guide, user & 
programmer guide, test plan. Please, notice that in some cases this might 
require some packaging work if you need to install components on top of 
baseline assets. 
Regarding the test-plan -- there are detailed guidelines sent by Juanjo 
earlier today. We need to add epics and features to the backlog in the 
wiki that cover the main functionality of the 'baseline' assets -- so that 
by the end of the month our backlog will cover all the functions that need 
to be tested once GEs are deployed in the testbed. Then for each feature 
we need to document the test cases, in the wiki too. 
Action Item [All, by Tue the following week, 26/6]: add to the wiki the 
necessary epics and features to cover all the testable functions of each 
GE, as well as test cases for each feature. We will review the results 
during our meeting on 27/6.
The testbed is supposed to be ready in the beginning of July. We will need 
to complete the installation and integration of our GEs in the testbed by 
the end of July, when we will need to have fully-functional cloud 
environment, with all the GEs (planned for July). We will discuss the 
details at our meeting on July 4th.

Regards, 
Alex

====================================================================================================
Alex Glikson
Manager, Cloud Operating System Technologies, IBM Haifa Research Lab
http://w3.haifa.ibm.com/dept/stt/cloud_sys.html | 
https://www.research.ibm.com/haifa/dept/stt/cloud_sys.shtml 
Email: glikson at il.ibm.com | Phone: +972-4-8281085 | Mobile: 
+972-54-6466667 | Fax: +972-4-8296112




From:        Alex Glikson/Haifa/IBM at IBMIL 
To:        "fiware-cloud at lists.fi-ware.eu" 
<fiware-cloud at lists.fi-ware.eu>, 
Date:        13/06/2012 03:53 PM 
Subject:        [Fiware-cloud] agenda 
Sent by:        fiware-cloud-bounces at lists.fi-ware.eu 



The main topic on the agenda for today's weekly call (in few minutes) is 
the June deliverables, as well as summary of FI-PPP education sessions. 

Regards, 
Alex 


====================================================================================================
Alex Glikson
Manager, Cloud Operating System Technologies, IBM Haifa Research Lab
http://w3.haifa.ibm.com/dept/stt/cloud_sys.html | 
https://www.research.ibm.com/haifa/dept/stt/cloud_sys.shtml 
Email: glikson at il.ibm.com | Phone: +972-4-8281085 | Mobile: 
+972-54-6466667 | Fax: +972-4-8296112
_______________________________________________
Fiware-cloud mailing list
Fiware-cloud at lists.fi-ware.eu
http://lists.fi-ware.eu/listinfo/fiware-cloud
_______________________________________________
Fiware-cloud mailing list
Fiware-cloud at lists.fi-ware.eu
http://lists.fi-ware.eu/listinfo/fiware-cloud
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.fiware.org/private/old-fiware-cloud/attachments/20120627/0aa0a630/attachment.html>