Attendees: IBM, Thales, UPM

1. Exploitation plans: need to send to EC by the end of the months updates 
(per partner)
2. Progress report: request for contributions
3. Backlog: sent separate email with guidelines, need to fix by next week 
towards delivery at the end of the month
4. Project roadmap: need to update the page. May need to apply some 
replanning if project extension is approved.
5. Hackaton: ongoing, requires support by some of the team members

Regards,
Alex