Manuel, I don't understand: during the last weeks (after the review in December), we have stopped our developments as asked. We concentrated on unplanned and unexpected tasks: packaging our SW so we have a clear endpoint and closing our documentation / examples apps. So, of course, the tracker was not updated (ie: postponed features) Do you want an entry in the tracker saying we are working on packaging / closing / documenting ? Please remember that internally, as I already said, we are NOT using an agile methodology (no choice: I must follow the company's process) and that everything related to the tracker is just an extra bureaucratic effort we have accepted just to ease the global project management (I guess it is the same for many other partners). I will therefore: - Add entries in the tracker (on WP4 and WP7 sides) to describe the "packaging" effort - Ask for costs from the time between the Commission decision (end of Dec) and the end of Jan for "packaging / documenting / closing properly our SW devt" (no new feature = nothing in the tracker). - Ask for costs in both WP4 and in WP7 as we have been doing from the beginning of the project. I don't believe it is really the right time to change anything now that we are at 4 days of the end of our development phase !!! - Officially announce that we will not go for the project extension after M36 as initially planned Note that our SW will NOT be open source as it was announced because we had to stop our developments and we still have proprietary code inside (unexpected stop). All the expenses starting on 1st of Feb will be for support (of course, if the Commission decides the Cloud Edge is to be kept in the list of funded GEs, we can still change all that). I hope you will share our vision Regards Henk PS: don't hesitate to call !!! From: MANUEL ESCRICHE VICENTE [mailto:mev at tid.es] Sent: mardi 28 janvier 2014 18:36 To: fiware-i2nd at lists.fi-ware.eu Cc: Heijnen Henk Subject: Backlog - updated dashboards Dear Partners, Get updated dashboards for I2ND chapter. Henk, please be aware that you have nothing scheduled at sprint level. If you were doing documentation, (any workitem), it would be wrong. Again, please, be aware that I won't allow cost to be charged when activity is not reflected in the tracker. [cid:image001.png at 01CF1CD4.4272FBB0] Thanks for cooperation!! Kind regards, Manuel ---------------------------- Manuel Escriche Vicente Agile Project Manager/Leader FI-WARE Initiative Telefónica Digital Parque Tecnológico C/ Abraham Zacuto, 10 47151 - Boecillo Valladolid - Spain Tfno: +34.91.312.99.72 Fax: +34.983.36.75.64 http://www.tid.es<http://www.tid.es/> ________________________________ Este mensaje se dirige exclusivamente a su destinatario. Puede consultar nuestra política de envío y recepción de correo electrónico en el enlace situado más abajo. This message is intended exclusively for its addressee. We only send and receive email on the basis of the terms set out at: http://www.tid.es/ES/PAGINAS/disclaimer.aspx -------------- next part -------------- An HTML attachment was scrubbed... URL: <https://lists.fiware.org/private/old-fiware-i2nd/attachments/20140129/ff88b6c0/attachment.html> -------------- next part -------------- A non-text attachment was scrubbed... Name: image001.png Type: image/png Size: 14223 bytes Desc: image001.png URL: <https://lists.fiware.org/private/old-fiware-i2nd/attachments/20140129/ff88b6c0/attachment.png>
You can get more information about our cookies and privacy policies clicking on the following links: Privacy policy Cookies policy