Dear partners,
     first of all let me say that this has not been an easy review ...
I summarize very briefly here the main points, and for who of you that may
be available, we can have a conf call tomorrow at 15.00 CET, usual phone 
bridge.

1) all our proposals have been accepted:
- D9.1 and D9.2 to M36
- D9.3 and D9.4 at M33
- all the available information will be included in the accompanying 
software deliverables
- additional chapter for the Handbook

2) the commission ask to stop the development of all the tools as far as 
they are mature enough.
This allow us to have enough effort for delivering the documents at 
best, especially the Handbook.

3) They haven't said anything about the costs review ...

I'll be out of office from 23/12 until 7/01 but I'll try to keep the 
emails under control, and I'll send
a more detailed plan proposal as soon as possible.

talk to you tomorrow,
BR
Davide