[Fiware-tools] Fwd: [Fiware-wpl] IMPORTANT: Extension of the project duration

Marcel Zalmanovici MARCEL at il.ibm.com
Wed Oct 23 14:15:20 CEST 2013


I don't see any problem with moving deliverables further into the future.
"Worst" case we finish planned work earlier and either have more testing 
time or can add new features.



From:   Davide Dalle Carbonare <davide.dallecarbonare at eng.it>
To:     "fiware-tools at lists.fi-ware.eu" <fiware-tools at lists.fi-ware.eu>, 
Date:   23/10/2013 10:24 AM
Subject:        [Fiware-tools] Fwd: [Fiware-wpl] IMPORTANT: Extension of 
the     project duration
Sent by:        fiware-tools-bounces at lists.fi-ware.eu



Dear Partners,
    please find below a main from Juanjo on the project extension.
I also attach the list of deliverables with some updates I've done.

We already talked about the project extension during our lasts conf
calls with all the partners are in favor of that.
The shift of the dates for our deliverable is from M33 to M36 that 
sounds acceptable from my side.
If you have some objection, please let me know in time to forward
them to Juanjo.

kind regards,
Davide


-------- Original Message -------- 
Subject: 
[Fiware-wpl] IMPORTANT: Extension of the project duration
Date: 
Wed, 23 Oct 2013 07:36:09 +0200
From: 
Juanjo Hierro <jhierro at tid.es>
To: 
fiware-wpl at lists.fi-ware.eu <fiware-wpl at lists.fi-ware.eu>, 
fiware-wpa at lists.fi-ware.eu <fiware-wpa at lists.fi-ware.eu>
CC: 
fiware-pcc at lists.fi-ware.eu <fiware-pcc at lists.fi-ware.eu>


Hi all,

  As we have discussed a couple of times, the EC has suggested an 
extension of the FI-WARE project duration for at least 4 additional 
months.   This was actually a recommendation given in the last review 
report.
 
  This was a topic that I have encouraged you to discuss with the teams in 
your respective chapters. 

  During our meetings, it was also agreed that extension of the project 
would mean a request to move the dates of those deliverables linked to 
release of software and accompanying documentation so that they change to 
be month 36 instead of 33.   Those deliverables linked to deployment of 
software on the FI-PPP Testbed and FI-LAB which were planned for month 36 
would also be delayed until month 40.   We didn't discuss this but I guess 
we would agree that some of the final reports to be produced should also 
be delayed from month 36 until month 40.

  So far, the only feedback I have got is that partners would be ok for 
the proposed extension, provided the mentioned changes in deliverable 
dates are incorporated.

  With all these considerations in mind, I have produced the attached 
updated version of the Deliverable List.   Changes are highlighted so that 
you can easily track them.   Of course, your feedback is welcome.

  Unless I hear about any objection from your side before this Friday EOB, 
I will submit an official  response to the EC announcing our agreement to 
extend the project duration another 4 months (i.e., until end of August 
2014), provided the changes we propose in the deliverable dates are 
accepted.    I will use the attached table as basis although I'm happy to 
incorporate some additional changes you may consider necessary.

  Best regards,

-- Juanjo

-------------
Product Development and Innovation (PDI) - Telefonica Digital
website: www.tid.es
email: jhierro at tid.es
twitter: twitter.com/JuanjoHierro

FI-WARE (European Future Internet Core Platform) Coordinator 
and Chief Architect

FI-PPP Architecture Board chairman

You can follow FI-WARE at:
  website:  http://www.fi-ware.eu
  facebook: http://www.facebook.com/pages/FI-WARE/251366491587242
  twitter:  http://twitter.com/FIware
  linkedIn: http://www.linkedin.com/groups/FIWARE-4239932



Este mensaje se dirige exclusivamente a su destinatario. Puede consultar 
nuestra política de envío y recepción de correo electrónico en el enlace 
situado más abajo.
This message is intended exclusively for its addressee. We only send and 
receive email on the basis of the terms set out at:
http://www.tid.es/ES/PAGINAS/disclaimer.aspx

[attachment "FI-WARE-DoW-Amendment5 deliverable list 
(version_date-13-07-17) DRAFT.docx" deleted by Marcel 
Zalmanovici/Haifa/IBM] [attachment "Attached Message Part" deleted by 
Marcel Zalmanovici/Haifa/IBM] [attachment "FI-WARE-DoW-Amendment5 
deliverable list (version_date-13-07-17) DRAFT DDC.docx" deleted by Marcel 
Zalmanovici/Haifa/IBM] _______________________________________________
Fiware-tools mailing list
Fiware-tools at lists.fi-ware.eu
https://lists.fi-ware.eu/listinfo/fiware-tools

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.fiware.org/private/old-fiware-tools/attachments/20131023/361dfac3/attachment.html>


More information about the Old-Fiware-tools mailing list

You can get more information about our cookies and privacy policies clicking on the following links: Privacy policy   Cookies policy