Karen,
I think I am lost. I fill in this, both PM and description input, here:
https://docs.google.com/document/d/1F99eFk44ckYUNcqOZNgeRtShDjuyohusVfO5y_dFUlI/edit#heading=h.gjdgxs

but this is not in the link you sent below.

Please check and clarify what is the reference file.

Regards,
Carlo

___________________________________________
Carlo Harpes
Managing Director
itrust consulting s.à r.l.

Office building: 55, rue Gabriel Lippmann L-6947 Niederanven
Phone: +352 2617 6212 (Reception)
mobile: +352 621  45 19 45
Headquarter: 18, Steekaul;  L-6831 Berbourg
Web:     www.itrust.lu<http://www.itrust.lu/>
mailto:  harpes at itrust.lu<mailto:harpes at itrust.lu>
r.c. lux B123183 – VAT: LU 21534655
___________________________________________
This message is restricted and may contain personal data; any unauthorized disclosure, use or dissemination, either whole or partial, is prohibited.
If you are not the intended recipient of the message, please notify the sender immediately.
itrust consulting s.à r.l. does not accept liability for any errors, omissions or even commitment in the contents of this message, except where supported by a written agreement with the receiver.

From: token-all-bounces at lists.fiware.org <token-all-bounces at lists.fiware.org> On Behalf Of Karen Vega
Sent: 27 April 2022 16:37
To: token-all at lists.fiware.org
Subject: [Token-all] Reminder: TOKEN Project interim report Internal deadline 29 April 2022 5 CET time

Dear All
Thank you, we have seen some of you active on the document!  https://docs.google.com/document/d/1gm5ryNWv3BL7rc1IFtVI7ywQcIZZebmCujjQKzUML3I/edit#<https://docs.google.com/document/d/1gm5ryNWv3BL7rc1IFtVI7ywQcIZZebmCujjQKzUML3I/edit>

Please remember we need to close this on Friday 29th, 2022 for internal revision. If any doubts Stefano and myself are reachable for support.

Thanks a lot

Kindest regards,

Karen

On Thu, Apr 21, 2022 at 11:22 AM Karen Vega <karen.vega at fiware.org<mailto:karen.vega at fiware.org>> wrote:
Dear All

We hope this email finds you well

Following up on Stefanos email I send this reminder of the deadline commitment of 29th of April ( Next week) agreed on the April EBM to have the
project interim progress report ready so Stefano can revise it.
Link to the simplified version  to complete here https://docs.google.com/document/d/1gm5ryNWv3BL7rc1IFtVI7ywQcIZZebmCujjQKzUML3I/edit#<https://docs.google.com/document/d/1gm5ryNWv3BL7rc1IFtVI7ywQcIZZebmCujjQKzUML3I/edit>

Stefano suggests providing only overall achievements and main outcomes in the period:  while the report covers the period: 1/1/2021-31/12/2021 the project check shall describe what was achieved till the day of the project check meeting itself.

Thank you for your engagement.

K

On Thu, Apr 21, 2022 at 4:50 AM Stefano De Panfilis <stefano.depanfilis at fiware.org<mailto:stefano.depanfilis at fiware.org>> wrote:
dear all,

here is a doodle (https://doodle.com/meeting/participate/id/e0RXQPKb) through which select the most appropriate slot for project check rehearsal.
please provide your preference by tomorrow eob at the very most.
since i did not receive any confirmation from the po to my previous email, i communicated to him that we consider 26th april as not feasible day for the project check (besides everything this day is the second day of orthodox easter, so its holidays in greece!).

agenda for the project check shall be something like:
project overall status - stefano - 40 minutes
wp1 - lynda - 30 minutes
wp3 - kostas - 30 minutes
wp4 - judith - 30 minutes
wp5 - angeles - 30 minutes
wp6 - adnan - 30 minutes

so, presentations shall last half of the slot duration as to allow questions from po and monitors.

besides, here is the link for the revised project interim progress report: https://docs.google.com/document/d/1gm5ryNWv3BL7rc1IFtVI7ywQcIZZebmCujjQKzUML3I/edit#<https://docs.google.com/document/d/1gm5ryNWv3BL7rc1IFtVI7ywQcIZZebmCujjQKzUML3I/edit>
as you can see i simplified it very much as this report shall provide only overal achievements and main outcomes in the period.

please note that while the report covers the period: 1/1/2021-31/12/2021 the project check shall describe what was achieved till the day of the project check meeting itself.

thank you for your prompt reaction on the matter.

ciao,
stefano

--
Stefano De Panfilis
Chief Operating Officer
stefano.depanfilis at fiware.org<mailto:charlotte.kotterman at fiware.org>
www.fiware.org<https://www.fiware.org/>
Mob: +393357542567
Skype: depa01
twitter: depa01

[https://nexus.lab.fiware.org/repository/raw/public/images/twitter1.png]<https://twitter.com/fiware>
[https://nexus.lab.fiware.org/repository/raw/public/images/fiware-logo2.png]



__________________________________________________________________________________________

You can get more information about our cookies and privacy policies on the following links:
- https://fiware-legal.readthedocs.io/en/latest/PersonalDataProtectionPolicy.html
- https://fiware-legal.readthedocs.io/en/latest/FIWARECookiesPolicy.html


token-all mailing list
token-all at lists.fiware.org<mailto:token-all at lists.fiware.org>

To unsubscribe from token-all mailing list, go to the information page of the list at:
https://lists.fiware.org/listinfo/token-all


--
Karen Vega
Senior Manager

karen.vega at fiware.org<mailto:karen.vega at fiware.org>
www.fiware.org<https://www.fiware.org/>


<https://www.linkedin.com/in/karenvega/>
Linked-In/Karen Vega<https://www.linkedin.com/in/karenvega/>
[https://nexus.lab.fiware.org/repository/raw/public/images/fiware-logo2.png]
 "The best preparation for tomorrow is doing your best today." H. Jackson Brown, Jr. American Author

[https://nexus.lab.fiware.org/repository/raw/promo/email_footer.png]<https://nexus.lab.fiware.org/fiware.signature>







--
Karen Vega
Senior Manager

karen.vega at fiware.org<mailto:karen.vega at fiware.org>
www.fiware.org<https://www.fiware.org/>


<https://www.linkedin.com/in/karenvega/>
Linked-In/Karen Vega<https://www.linkedin.com/in/karenvega/>
[https://nexus.lab.fiware.org/repository/raw/public/images/fiware-logo2.png]
 "The best preparation for tomorrow is doing your best today." H. Jackson Brown, Jr. American Author

[https://nexus.lab.fiware.org/repository/raw/promo/email_footer.png]<https://nexus.lab.fiware.org/fiware.signature>





-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.fiware.org/private/token-all/attachments/20220430/f01d94dc/attachment-0001.html>
-------------- next part --------------
An embedded and charset-unspecified text was scrubbed...
Name: ATT00001.txt
URL: <https://lists.fiware.org/private/token-all/attachments/20220430/f01d94dc/attachment-0001.txt>


More information about the Token-all mailing list

You can get more information about our cookies and privacy policies clicking on the following links: Privacy policy   Cookies policy