[Fiware-wpl] [Fiware-wpa] Presentation on workplan for phase 2 projects

Juanjo Hierro jhierro at tid.es
Fri Feb 1 10:28:18 CET 2013


Hi all,

  Please find enclosed an updated version where I believe I have been able to cope with all your comments:

=== From Pascal:

>> Only one suggestion from my side: not to wait for September to have the f2f meeting with the capacity building project. For me the sooner would be the better (even if the first of a series ...).

  Done, see slide 10.


=== From Thorsten:

>> Introduce one or two slides on the _actual_ and planned availability and features/components of FI-WARE in the beginning of the document. This information probably is information they are anyway "longing" for and might put us in a good position.

>> - what does FI-WARE provide?
>>     - development platform for future internet applications
>>     - business ecosystem around future internet applications and services
>>     - one UC example and what was done in phase 1


>> - major milestones for FI-WARE
>>     - release 2 of the platform & components
>>     - Opening of the open innovation lab & "general availability" of fi-ware testbed to third parties

>> The down-side is that there might be discussions on details, so potentially make it an agenda-item on your presentation & put it on the end of the presentation, then all the UC will definitely stay in the room  and wait for this part, consuming the rest of the information hopefully

  I have incorporated a number of slides at the beginning of the presentation dealing with most of this.   There are hyperlinks in several places so that we can navigate and show the resources available and drill down in the details if needed

=== From Stefano:

>> i do agree with thorsten.
>> this can be done by simply showing the excel file with usage from the
>> current uc (easy and effective) and on that you can say many things.

  I have included a reference to this popular shared spreadsheet on slide 7

>> i'd suggest also a slide on the stockholm example.

  could you provide that ?

>> agree with pascal we should have meetings with xifi much earlier and
>> also in the goal os that slide clarify that the open innovation lab is
>> an already realiable and existing infrastructure!

  as mentioned, I believe concerns covered in slide 10

>> we should also provide a tutorial (june ?) about the tracker (i think
>> a slide with a picture of it is necessary just to show how it looks
>> like and that this will be their main communication tool with us and
>> the whole ppp about technology issues.

  covered in slide 9

>> i do not think the "deplyment trials" slide time schedule is feasable
>> prior to discuss this f2f with the commission. phase 3 projects are
>> expected to start in april 2014 and they need available the uc
>> platform up and running.

  generated a new version of slide 12



  Slides 7-12 will be decorated with photos on the right as in slide 5.   Of course, any further comment is welcome.

  I still need the slide that WP10 should provide elaborating on the validation process we that the UC trial projects should follow !!

  Cheers !


-- Juanjo


On 30/01/13 16:13, Juanjo Hierro wrote:
Hi all,

  Please find enclosed a draft version of the presentation regarding
workplan to be presented during the negotiation workshop next week.

  I have tried to capture all what we discussed during our meeting in
Rome.   I'm still working on it but I guess there is already enough
content as to start gathering your feedback/comments.

  I would kindly ask you to provide your comments before noon tomorrow,
so that I can close an almost final version before the PCC meeting on
the afternoon

  Cheers,

-- Juanjo

-------------
Product Development and Innovation (PDI) - Telefonica Digital
website: www.tid.es<http://www.tid.es>
email: jhierro at tid.es<mailto:jhierro at tid.es>
twitter: twitter.com/JuanjoHierro

FI-WARE (European Future Internet Core Platform) Chief Architect

You can follow FI-WARE at:
  website:  http://www.fi-ware.eu
  facebook: http://www.facebook.com/pages/FI-WARE/251366491587242
  twitter:  http://twitter.com/FIware
  linkedIn: http://www.linkedin.com/groups/FIWARE-4239932


________________________________

Este mensaje se dirige exclusivamente a su destinatario. Puede consultar nuestra política de envío y recepción de correo electrónico en el enlace situado más abajo.
This message is intended exclusively for its addressee. We only send and receive email on the basis of the terms set out at:
http://www.tid.es/ES/PAGINAS/disclaimer.aspx



_______________________________________________
Fiware-wpa mailing list
Fiware-wpa at lists.fi-ware.eu<mailto:Fiware-wpa at lists.fi-ware.eu>
http://lists.fi-ware.eu/listinfo/fiware-wpa





________________________________

Este mensaje se dirige exclusivamente a su destinatario. Puede consultar nuestra política de envío y recepción de correo electrónico en el enlace situado más abajo.
This message is intended exclusively for its addressee. We only send and receive email on the basis of the terms set out at:
http://www.tid.es/ES/PAGINAS/disclaimer.aspx
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.fiware.org/private/fiware-wpl/attachments/20130201/b2a53e44/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: FI-WARE presentation on workplan for FI-PPP phase 2 v13-02-01.pptx
Type: application/vnd.openxmlformats-officedocument.presentationml.presentation
Size: 1775837 bytes
Desc: not available
URL: <https://lists.fiware.org/private/fiware-wpl/attachments/20130201/b2a53e44/attachment.pptx>


More information about the Fiware-wpl mailing list

You can get more information about our cookies and privacy policies clicking on the following links: Privacy policy   Cookies policy