[Fiware-testbed] Fwd: [Fiware-pcc] Fwd: FI-WARE: extract executive summary draft review report

stefano de panfilis stefano.depanfilis at eng.it
Mon Jul 30 13:07:06 CEST 2012


dear all,

please find forwarded the extract from the executive summary review report.
there is a looooot to do for the whole project to be on a safe a nd
succesfull track, but this well know by everybody involved in the project.

concerning wp10 our deliverables have been all accepted despite the very
late submission.
now we ALL, not only taks t10.2 (!!!), are at the core of the next weeks a
dn project success, so i do expect maximum committemnt for the next coming
weeks and few months (month 18 = 31st cotober 2012)!!!

concerning the report as such we have two "check points" to fully satifsy
(of course in addition to what is in the dow):

- "2. Public availability matrix of use cases using the GEs; continuous
update of the matrix, month 15 & thereafter"
- "5. Testbed in operation, feedback from UC projects on using the testbed,
month 17"

there is also this "check point", which is shared by the whole project:
- "9. live demonstration fo the fi-ware testbed with develoyed ge software,
next review meeting"

talk to you this wednesday!

ciao,
stefano

---------- Forwarded message ----------
From: Juanjo Hierro <jhierro at tid.es>
Date: 2012/7/30
Subject: Re: [Fiware-pcc] Fwd: FI-WARE: extract executive summary draft
review report
To: "fiware-wpl at lists.fi-ware.eu" <fiware-wpl at lists.fi-ware.eu>, "
fiware-wpa at lists.fi-ware.eu" <fiware-wpa at lists.fi-ware.eu>, "
fiware-pcc at lists.fi-ware.eu" <fiware-pcc at lists.fi-ware.eu>


 Hi,

  Just wanted to add the fiware-pcc, in order to make the dissemination
more complete.

  Don't hesitate to use this as a tool to demonstrate members of your team
the need that they take things seriously and deliver.

  Best regards,

-- Juanjo



On 30/07/12 10:58, Juanjo Hierro wrote:

Dear colleagues,

  We have just received the following extract of the executive summary
draft review report.

  We haven't had time to review it.   But certainly the review report is
not as positive as we thought after the first year review meeting.

  Overall, it is worth to highlight that the project's assestment is:

   - Unsatisfactory progress (The project has failed to achieve key
   objectives and/or is not at all on schedule)"


  This, among other things, confirms us that the recent measurements put in
place were required.

  Now, it's critical to demonstrate that we are going to deliver what was
due and that the testbed will not get delayed.
   We'll come with additional comments later.

  Best regards,

-- Juanjo


-------- Original Message --------  Subject: FI-WARE: extract executive
summary draft review report  Date: Mon, 30 Jul 2012 08:42:05 +0000  From:
<Arian.ZWEGERS at ec.europa.eu> <Arian.ZWEGERS at ec.europa.eu>  To:
<jimenez at tid.es> <jimenez at tid.es>, <jhierro at tid.es> <jhierro at tid.es>  CC:
<jdps at tid.es> <jdps at tid.es>, <mcp at tid.es> <mcp at tid.es>,
<CNECT-ICT-285248 at ec.europa.eu> <CNECT-ICT-285248 at ec.europa.eu>

 Dear all,



Below is an extract from the draft executive summary of the draft M12
review report.

The extract may deviate from the executive summary in the final version of
the review report.



It is sent since it contains some information, e.g. about deliverable
acceptance, that you may want to know asap.



Best regards,

Arian.



======================



The objectives of the project during this period remain unchanged, but are
brought into sharp focus due to the delay of two months plus now apparent,
and the critical need to release the complete and comprehensive Generic
Enabler (GE) Open Specifications and accompanying reference code as soon as
possible in order to not risk destabilizing the entire FI PPP.



Many primary technical deliverables expected at M12 are not yet available,
which is extremely poor progress given that they are some of the main
achievements planned for Month 12 and create the first useable foundation
for Use Cases projects to build upon. Compounding this failure is the poor
quality and incompleteness of various technical deliverables; a quite
astounding result given the resources available to the project.



According to the Description of Work (DoW), the main achievements for this
period should be the first version of the GE open specifications, software
prototypes and related guidance material and test plan. Only the
specifications were delivered so far. However, they are inadequate for
communication and unified understanding with the Use Case projects, are
not  of the required quality to serve the needs of those projects, and do
not provide sufficient basis for practical implementation by software
developers - all of which are fundamental to the rationale for and
objectives of FI-WARE. It is unclear in many of the GE specifications which
are the reusable and commonly shared functions, and which usage areas
across various sectors would utilize these GEs. There are also no details
on the protocols that support interoperability with other GEs or third
party products or how this interoperability would be achieved. Moreover, a
consolidated and consistent presentation of the specifications is still
missing.



There is a lot of confusion about what the GEs really are, or meant to be,
within the FI-WARE consortium, and most probably the UC projects, not to
mention the world at large. They are a mixed bag, including functional
descriptions, specifications of (not necessarily well-defined) technical
functions, specification of access and other operational protocols,
specification of access to other existing “modules”/“components”/”devices”
and so on, specifications to enable interfaces between existing protocols,
specifications to enable deployment of other collection of protocols as
“engines”, etc.



As mentioned in the DoW, "GE Open Specifications will contain all the
information required in order to build compliant products which can work as
alternative implementations of GEs developed in FI-WARE and therefore may
replace a GE implementation developed in FI-WARE within a particular
FI-WARE Instance." However, given the current state of the GE deliverables,
there are severe doubts about how a FI-WARE instance (“platform”) could be
built from the GEs without a massive amount of “imagination” and tweaking
to make them work together. There are also severe doubts about how a
“Future Internet Application” could be portable across different FI-WARE
Instances that implement the (same set of?) GEs that the Future Internet
Application relies on.



The GEs as currently defined are not, by themselves, implementable in the
sense of delivering a practical software solution (“platform”). This is
compounded by the difficulty of understanding what is really meant by a
“coherent” set of GEs. Some GEs seem to have closer inter-relationships
than others.



Notwithstanding the (useful) clarifications and information orally provided
at the review meeting, the inadequate and indeed scarce information within
these specifications and the discrepancies between the Technical Roadmap
and the available GE contents lead the reviewers to cast doubts on the
project achievement so far, and its prospect.



*FI-WARE failed to meet its milestones for Month 12. *



Given the above, *technical progress of the project for the first year is
unacceptable*. Moreover, any further delay is likely to significantly risk
integrity of the entire FI-PPP and the smooth transition to Phase 2.



The consortium made a generally positive and concerted effort so far as the
review meeting is concerned. It presented itself as a credible team. The
verbal presentations made at the meeting were typically more informative
and explanatory than the written deliverables would lead readers to expect
(some material within the presentation, such as the matrix of use cases
using GEs, is highly appreciated by the reviewers). With evident technical
capability, but lack of timely and quality delivery, *managerial action is
an absolute and urgent must for an accelerated FI-WARE recovery, and to
ensure that the FI-PPP programme will deliver meaningful innovations*.



Collaboration with Use Case projects appears to be improving markedly
thanks to key face-to-face training weeks, and enhancements to the way the
Fusion Forge system is managed. However, there are still significant issues
concerning the processing and documentation of the requirements/backlogs. *A
main conclusion from the review is that the Use Cases requirements are
still not considered as high priority by FI-WARE*. Feedback from Use Case
projects, including implications for the technology perspective and choices
made by FI-WARE, should be (more visibly) taken into account and
demonstrated as such. Traceability is crucial for the credibility of the
FI-WARE technical deliverables and uptake beyond the consortium; and
accountability is required to justify financing from the public purse.



The recently conducted architecture training weeks should be used as a
stepping stone towards building an FI-PPP “culture” between all Programme
participants. More such sessions should be planned, particularly around the
test-bed integration deployment and use of the DevComE toolset. For its own
part, DevComE is presently a positive highlight of the project. Integration
planning for the test-bed is sound and detailed.



The testing and the integration activities are among the project
highlights. Both are carefully planned and well specified. As the
development of the GEs is delayed, the integration activities still lack
concreteness in terms of specific scenarios in which several of the GEs
will be involved, which is a pity.



Work undertaken regarding communication and dissemination is showing
significant advancement, albeit with still substantial opportunity for
improvement.



Given the overall delay in the work plan, the postponement of many key
deliverables, and the insufficient quality (and quantity) of the technical
specifications, the reviewers consider that the resources were not utilized
effectively within the first project year.



The consortium has put reasonable effort into analysing and positioning
FI-WARE in the current market context. The exploitation within the scope of
“Smart Cities” is promising and welcome, but the Use Cases projects should
be targeted as prime users. The business strategy is however absent, in so
far that no credible and preliminary quantified business case has been
presented yet. The consortium’s position that the business case will arrive
in the second year of the project is a matter of serious concerns; for
example, the reviewers have the strong impression that nobody in the
consortium has any notion of the overall amount of investment required to
take FI-WARE results to the market, and the work presented is clearly
(still) lacking substantive input from the business departments of the
industrial partners. Despite the extensive comments in the Month 6 Review
Report and notwithstanding the voluminous deliverable D11.2.1, there is
still no unified or compelling marketing message, including no compelling
unique selling proposition, of the FI-WARE results. The individual
exploitation plans of the partners are timid. There is inadequate
consideration of third party development and SME exploitation at the
business level. The globalisation dimension of the exploitation plan is
unconvincing. The consortium is reminded that the success of FI-WARE
depends on the delivery of a genuine global solution, exploitable by
partners inside and outside the consortium and beyond Europe. In
summary, *there
is a glaring and alarming discrepancy between the high ambitions of FI-WARE
given in the DoW and the very limited perspective of exploitation offered
so far.*



The reviewers are disappointed that many of the recommendations made –
dating back to the Month 6 review or even earlier - have not been
sufficiently considered. Additionally, the reviewers are frustrated by the
pattern of (extremely) late submission of the majority of the deliverables,
and hastily communicated rescheduling of other deliverables with debatable
arguments. Such behaviour is not acceptable in the business world; it is
equally unacceptable in the context of European collaborative activity,
especially in view of the public funding involved.





b.            Recommendations concerning the period under review



The following deliverables require re-submission:

•             D2.3.1 by Month 15 (from Month 9 review)

•             D2.4.1 by Month 15 (from Month 9 review)

•             D2.1.2 by Month 18

•             D3.1.1 by Month 18

•             D4.1.1 by Month 18

•             D5.1.1 by Month 18

•             D6.1.1 by Month 18

•             D7.1.1 by Month 18

•             D8.1.1 by Month 18

•             D11.1.1 by Month 18

•             D11.2.1 by Month 18

•             D11.3.1 by Month 18





The following recommendations are reiterated from the Month 6 review report
(with the timeframe for R[1][2]1 adjusted in light of the Month 9 review)
and were expected to be addressed in a satisfactory manner by the Month 12
review (original recommendations re-produced in italics):



*R [1-3]1.               Given FI-WARE’s intent to remain domain neutral, a
comprehensive technology map must be created that clearly and unambiguously
illustrates the relationships between all Generic Enablers to be produced
by FI-WARE. This was expected to be documented in deliverable D2.3.1
originally due Month 9, for which re-submission is now due Month 15. *

Still to be addressed in the forthcoming resubmission of D2.3.1 due Month
15.



*As regards the “transparent encompassing architecture” for FI-WARE as a
whole also asked for already in the first recommendation of the review
report at M3, we advise the consortium to keep in mind and log this
recommendation, and re-visit it in 2013, after the projects selected under
Phase 2 have joined the FI PPP.*



*R [1-3]3.               Ensure meaningful interaction with standards
bodies including Internet-related standards groups such as the IETF, the
W3C, the IEEE, the ITU-T, the OMA, and the 3GPP/2. This is expected to be
reported in deliverable D12.3.2 due Month 12 and/or deliverable D11.4.1 due
Month 9.*

Still to be addressed in the forthcoming D11.4.2 due Month 15.



*R [1-3]6.               Ensure there is a focus on attracting a
development community for FI-WARE, and not only within the FI-PPP, but
where possible within the partner organisations and the open community of
potential users. This is expected to be considered in relation to
deliverable D2.5.1 and reported in deliverable D12.2.2.*

Still to be addressed in the forthcoming D2.5.1.



*R [1-3]7.               As there is substantial reliance on external
technology sources, e.g., other FP7 projects and open source projects,
contingencies should be prepared which address what actions to take should
those projects fail to deliver, or are delayed with planned delivery upon
which FI-WARE depends. This is expected to be documented in deliverable
D1.1.2 due Month 12.*

The sourcing of technology is still not sufficiently clear. Contingency
planning is still not adequately provided for or documented in D1.1.2.
Please provide an adequate plan in the online version of the Project
Management Handbook asap.



*R [1-3]8.               There is a reasonable likelihood that FI-WARE
chapters will be unable to achieve all that they would like to. A risk
mitigation strategy should be put in place for this, with thought given in
advance on how the project plans to prioritise resources if insufficient
resources are available to cope with all planned work. This is expected to
be documented in deliverable D1.1.2. The consortium is reminded that effort
and funding allocations in the DoW are indicative and not sacrosanct.*

A robust risk management strategy is still missing from D1.1.2. Please
provide such a strategy in the online version of the Project Management
Handbook asap.



*R [1-3]9.               Make sustained effort to enrol the support of
stakeholders from the business and marketing departments of all major
commercial partners in the project. External to the consortium,
dissemination should go considerably beyond the “traditional groups” that
are usually targeted for dissemination in FP7 projects. This concerns both
the RTD communities and the business communities at large, within as well
as outside Europe. Consumer organisations should also be considered and
inputs be sought, to make sure that the FI-PPP results will be successfully
adopted by the mass market. This is expected to be reported in deliverable
D12.2.2.*

Progress has been made in relation to dissemination. The active involvement
and support of the business and marketing personnel from the industrial
project partners is still largely absent.



*R [1-3]10.             Ensure that planning of the Open Calls starts early
and the Open Calls are inclusive enough to attract any prospective
submitters including specialist SMEs (without making a priori assumptions
about who might be interested in the calls). The Open Calls should be used
as a strategic opportunity for disseminating FI-WARE to FI stakeholders and
engaging their interest in FI-WARE outputs. The Open Call processes and
experience, including lessons learnt, should be documented and assimilated
by the consortium for subsequent calls, and included in the relevant
editions of deliverable D1.2.x for reporting and auditing purposes. Please
take into full account our remarks on the management and administration of
the Open Calls in Section 1a of the previous (M6) Review Report, and
clarify the rationale for the selection of the topic(s) for the forthcoming
first Open Call and to what extent the use case projects have a voice in
the topic selection in the first and subsequent calls.*

The reviewers are still awaiting the reporting of the first Open Call.
Progress to be re-assessed in relation to the planning/reporting of the
next Open Call in the forthcoming D1.3.2.



*R [1-3]11.             The reviewers cannot over-emphasise the importance
of exploitation planning, including detailed documentation of IPR
management. In our view, this is also intimately linked to enablement of
third party exploitation. Please refer to our remarks in Sections 1a and 1b
of the previous (M6) Review Report. It is obvious that high expectations
are placed by the reviewers on deliverables D11.2.1 and D2.5.1 due Month
12. Please do not treat this as a paper exercise for satisfying the
reviewers. Instead, they should be treated as initial blueprints for
realistic business models backed by genuine commitment from especially the
industrial partners.*

Unsatisfactory addressed. Exploitation planning lacks credibility and
market traction. To be addressed in the resubmission of D11.2.1 due M18.



*R [1-3]12.             All future deliverables should continue to be made
available to the reviewers in pdf format. They should also be submitted on
time. The consortium should investigate whether posting such files on its
website or wiki might provide value for potential users, in addition to the
wiki pages (at least those files relating to key deliverables). Please
report the findings of the investigation at the next review.*

Unsatisfactory addressed. Large numbers of deliverables not submitted on
time, yet again. Others have been rescheduled in a hasty manner. The
reviewers strongly recommend corrective actions.

Additionally, the reviewers request that project deliverables be made
available as a consolidated file for future reviews.

The consortium has no inclination to make deliverables available in a file
format, other than to the EC and reviewers for pure compliance purposes,
after evident resistance. The need to investigate the usefulness of such
files to would-be users was dismissed.



*R [1-3]13.             Improve the usefulness and attractiveness of the
project website: make the information (even) more easy to find, bearing in
mind that users might not be familiar with the FI-PPP; enhance the website
as a marketing tool to would-be third parties and ‘customers’ of FI-WARE
results (make the website answer the question to companies not involved in
EU funded activities: why should I be interested in what FI-WARE is doing,
and what is in it for me?). Consider the use of creditable Search Engine
Optimization techniques.*

Unsatisfactorily addressed – no evidence of website improvement as a
marketing tool. Significant improvement required for Month 17.

The consortium is also encouraged to bring forward the implementation of
the FI-WARE GE portal (not in DoW, but highly welcome) currently planned
for Year 3.



*R [1-3]14.             Put in place contingencies for loss of key people
from the project. This is expected to be documented in deliverable D1.1.2.*

Recommendation addressed to some degree, for example by involving WP
leaders in the management of backlog. Please provide a clear update in the
online version of the Project Management Handbook asap.



Recommendations still outstanding from the initial review of D2.2.1:



*•             R2: the relationship between GEs and the Specific Enablers
needs to be clarified and documented, bearing in mind that the former are
potential candidates for standardisation in due course, and the latter are
critical from the view point of making business out of FI-WARE results.
Documentation is now expected at Month 9 with deliverable D2.3.1.*

Still to be addressed in the resubmitted version of the D2.3.1 due Month
15.



*•             R9: The requested delivery schedule for the GEs, or at a
minimum indication of prioritisation, has not been presented. This is now
expected for deliverable D2.4.1 at Month 9. The information should be made
visibly available in the public domain.*

Still not addressed, with mismatches between the Backlog, the Technical
Roadmap and the Open Specifications delivered; To be addressed in the
resubmitted version of the D2.4.1 due Month 15.





c.             Recommendations concerning future work



R[3]15.  Ensure that the quality of the GE specifications is high and
consistent. Use GE specification for WP8 as a template for all other WPs.



R[3]16.  Clean up the backlog, and keep it up to date at all times.
Specific resources must be dedicated to this.



R[3]17.  Focus on delivery of critical-path, high-priority (for the Use
Cases) GEs.



R[3]18.  GE code releases must be synchronized with GE priorities indicated
by Use Case projects.



R[3]19.  Ensure that architectural documentation clearly and unambiguously
indicates the trace of source requirements and justification.



R[3]20.  Transparency and visibility in what was delivered and what is
going to be delivered by the consortium in all future FI-WARE Releases.



R[3]21.  Meeting the “check points” set by the reviewers.



For the next period leading up to the M18 review, the reviewers will be
monitoring and assessing project progress against the following key “check
points”, in addition to DoW compliance and assessment of the project
deliverables due:



1. Technical Paper including common usage scenarios for the GEs for wide
dissemination (incl. to Use Case projects and third parties), month 15

2. Public availability matrix of use cases using the GEs; continuous update
of the matrix, month 15 & thereafter

3. FI-WARE software release, month 15

4. Public availability of the SAP GEs in WP3, month 15 (done)

5. Testbed in operation, feedback from UC projects on using the testbed,
month 17

6. Enhancement/re-design of the current website for impact creation, month
17

7. Hold additional architectural weeks, develop training plan for use of
the DevComE framework, consider inviting 3rd party developers, month 18

8. Develop and publish a plan for fostering developer communities, month 18

9. Live demonstration of the FI-WARE test-bed with deployed GE software,
Next review meeting

10. Presentation by senior business personnel from the main commercial
partners of the consortium (at a minimum: TID, SAP, TI, Orange/FT) on
corporate plans to bring the FI-WARE key results to the market, Next review
meeting



R[3]22.  For the next period overall project resource allocation should be
reviewed to identify the specific weaknesses leading to the failings
identified in this review project; resources should be re-planned and
re-allocated to rectify the failings where necessary.





d.            Assessment



Unsatisfactory progress (The project has failed to achieve key objectives
and/or is not at all on schedule)





==============================



Some other considerations:



After one year in the project, one may want to evaluate what has been
achieved, esp taking into account that 12 MEuro has been spent. A specific
feature of the first reporting period, and a direct result of the delays,
is that efforts have been spent on tasks that did not result in submitted
deliverables. The economy, effectiveness and efficiency of these efforts
can therefore not be evaluated.



More importantly, after one year in the project, one may want to evaluate
what can be realistically achieved at the end of the project:

-          The status and maturity of single GEs differ a lot. More
consistency and maturity in the specification of GEs needs to be achieved.
The litmus test is that these specifications need to be sufficiently mature
and complete so that independent software developers can use them to
develop implementations that are interchangeable. Prospect: good.

-          It is not clear to what extent the GE Open Specifications
satisfy the requirements from use cases, FI-WARE organisations, or
otherwise. There is a risk that at the end of the project the GE Open
Specifications do not satisfy the requirements of the use cases.

-          The baseline assets of each individual GE are not clear. Partly
because of this, the roadmap is not clear. At the end of the project, there
will be reference implementations, no doubt, but it is not clear to what
extent the GE Open Specifications follow the existing baseline assets or
v.v. There is a risk that the reference implementations do not satisfy the
requirements of the use cases.

-          The IPR protection of the reference implementations is unclear.
At the end of the project, the use cases need clarity on this. It is
essential that this information becomes available as soon as possible.

-          Likewise, the exploitation plans of the owners of the reference
implementations are unclear. At the end of the project, the use cases need
clarity on this. It is essential that this information becomes available as
soon as possible.

-          The division of budgets in FI-WARE is (largely) based on the
existence of baseline assets. The more baseline assets a partner brought
into the project, the larger its budget in FI-WARE. The advantage is that
the work does not start from scratch. It is likely that these baseline
assets are typically proprietary solutions. It can be expected that
partners will give priority to their baseline assets, further developing
these assets, and give less priority to fulfilling use case requirements.
Although access to these assets by use case projects after the end of the
FI-WARE project is addressed by clause 41, the exact conditions for access,
the availability of the assets, and their maturity are unknown. This leaves
use cases, possible FI-WARE Instance providers, and third party application
developers in an uncertain situation, and clarity is necessary.

-          There is a high risk that current developments on GE reference
implementations do not fulfil the requirements of the use cases. This could
be accepted to some extent if these reference implementations would be
based on clear requirements from the business departments of the technology
providers, and if there were clear exploitation plans for these reference
implementations. In such situation, usefulness to use cases would be offset
by wide availability and accessibility. However, at the moment there is a
high risk that at the end of the FI-WARE project the reference
implementations will not fulfil the requirements from the use cases AND
will not be accessible.



The month 18 review and the Call 2 evaluation will provide an opportunity
to analyse the situation with respect to a) the FI-WARE GEs and their
reference implementations, b) the priorities of the phase 2 use cases, and
c) the commitments of the FI-WARE beneficiaries.

Regarding the FI-WARE GEs and their reference implementations, information
is needed a.o. concerning:

-          The final list of GEs for which Open Specifications will be
written

-          The extent to which these GEs fulfil requirements (from all
sources), providing justification and accountability

-          For each GE: the reference implementation(s) of the GE

-          For each GE reference implementation: the baseline asset(s) upon
which the reference implementation will be based, the current status, the
owner, the relation to other GE (reference implementations)

Regarding the phase 2 use cases:

-          The list of GEs the phase 2 use cases plan to use, and their
priority

-          The list of GE reference implementations the phase 2 use cases
plan to use, and their priority

Regarding the commitment of the FI-WARE beneficiaries:

-          For each GE reference implementation: the conditions under which
it will be available for FI-PPP programme participants and third parties
beyond the lifetime of FI-WARE



With respect to the last point, stated intentions in confidential
exploitation plans are not sufficient. True commitment and therefore true
assurance of the use cases and third parties of the sustainability of their
efforts building on FI-WARE can be shown via e.g. a public statement by the
GE reference implementation IPR holders. Such a public statement could
follow lines as sketched below:

-          "Our developments in FI-WARE/FI-PPP will be made available as
open-source, and/or

-          Our developments in FI-WARE will be proprietary, conforming to
the GE Open Specifications, and we guarantee that they will be available on
the market as of [date] under FRAND conditions and will be available for at
least [y] years. The exact conditions will be specified within [x] months.
In case our companies determine the product will no longer be commercially
offered, the source code will be made available as open source and donated
to [xyz], and/or

-          Company X is developing an implementation of a certain GE.
Within FI-WARE, an open source reference implementation of the same GE is
being developed. Company X builds a proprietary implementation, outside the
FI-WARE project, using own funds, and/or

-          Our companies encourage the development of multiple
implementations of a certain GE, will develop a reference implementation
for each of the specified GEs within the context of the FI-WARE project,
using public money, and will develop additional proprietary implementations
[for GEs g,h,k] using own funds

-          We commit to safeguard the evolution and nature of the GEs for
at least [x] years after the FI-PPP programme.

-          Etc"











------------------------------

Este mensaje se dirige exclusivamente a su destinatario. Puede consultar
nuestra política de envío y recepción de correo electrónico en el enlace
situado más abajo.
This message is intended exclusively for its addressee. We only send and
receive email on the basis of the terms set out at.
http://www.tid.es/ES/PAGINAS/disclaimer.aspx

_______________________________________________
Fiware-pcc mailing list
Fiware-pcc at lists.fi-ware.eu
http://lists.fi-ware.eu/listinfo/fiware-pcc




-- 
Stefano De Panfilis
Chief Innovation Officer
Engineering Ingegneria Informatica S.p.A.
via Riccardo Morandi 32
00148 Roma
Italy

tel (direct): +39-068307-4295
tel (secr.): +39-068307-4513
fax: +39-068307-4200
cell: +39-335-7542-567
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.fiware.org/private/old-fiware-testbed/attachments/20120730/b7cc3b5f/attachment.html>


More information about the Old-Fiware-testbed mailing list

You can get more information about our cookies and privacy policies clicking on the following links: Privacy policy   Cookies policy